Integrated MOPU and Wellbay Platform Solution for Early Field Production

A marginal offshore field required a fast and cost-effective route from concept to production. 2H delivered end-to-end engineering and execution support, enabling the development of a safe and efficient early production system within a demanding schedule.

Location

Nigeria

Location

Nigeria

Location

Nigeria

Background

A newly established oil and gas operator acquired a marginal offshore field located in shallow water and was met with the challenge of developing an unfamiliar asset under an aggressive schedule so they could drill the exploration well and achieve first production as quickly as possible.

The development concept centred on an early production system (EPS) using a jack up rig barge retrofitted with production processing facilities and a crude offloading system. The operator needed a partner capable of delivering end-to-end engineering and execution support, from concept development through to construction and offshore installation oversight, to transform the project from concept to reality within a demanding timeframe.

Project Scope

2H was engaged to provide comprehensive engineering and execution management across several critical workstreams:

  • Field development planning: Field development planning support and conceptualisation of a phased development for the facilities to reduce capital outlay and risk.

  • Detailed engineering of the wellbay platform: Full detailed design of the wellbay platform structure was carried out to support the early production phase, engineered and built in less than four months.

  • Execution management: Management of the procurement, construction, and offshore installation of the wellbay platform; qualifying, selecting and coordinating suppliers and fabrication yards to maintain the compressed delivery schedule while managing cost and risk.

  • FSO mooring & offloading jumper engineering: Design of the offloading system, including the FSO mooring arrangement and offloading jumper, and supported the procurement and management of associated suppliers.

  • Concept engineering of the permanent process facility: Developed the permanent production concept, defining the process architecture for a process platform to be deployed in the final phase of the field development. The work focussed on assessing the feasibility of a light-weight jacket.

Platform Design Solution

The development concept incorporated a jack-up rig retrofitted as a mobile offshore production unit (MOPU), equipped with production processing and crude offloading facilities to support early field production. Rather than pursuing a conventional fixed platform or FPSO development, 2H’s developed an approach that leveraged existing marine assets and adapted them enabling a faster and more cost-effective route to first oil. The wellbay platform was specifically designed to interface with the MOPU and accommodate the initial production wells, while the FSO mooring and offloading jumper provided a reliable crude export solution. The concept eliminated the need for a dedicated installation vessel, as the jack-up rig was used for both wellbay platform installation and subsequent production operations.  

Challenges

The project presented several notable challenges that demanded both technical ingenuity and rigorous project management:

  • Aggressive schedule: The overriding programme constraint required the wellbay platform to progress from engineering through fabrication to loadout-ready status in under six months. Every workstream had to be carefully sequenced and fast-tracked without compromising quality or safety.

  • Supply chain complexity: Procurement and fabrication in the Nigerian market introduced logistical and supply chain challenges, requiring close supplier engagement and proactive risk management by the 2H team to avoid delays.

  • MOPU retrofit integration: Retrofitting a jack-up rig with production processing and offloading systems demanded careful integration engineering to ensure safe, reliable operations within the constraints of the existing vessel.

  • Limited asset information: Availability of design data for the floating storage and offloading vessel was limited, requiring 2H to identify and manage the execution of detailed surveys to engineer a robust offloading system and enable successful modification program.

  • Marine asset certification risks: Delays to the jack-up drilling rig schedule created a risk of key marine asset certificates expiring before installation, requiring careful coordination and contingency planning to maintain project viability and delivery schedules.

Results

2H successfully delivered end-to-end engineering and execution support, enabling the operator to implement the design concept to a production ready state. The wellbay platform was engineered, fabricated, and prepared for loadout in under six months - a significant achievement given the technical, logistical and supply chain complexities with offshore developments in Nigeria.

Engineering of the FSO mooring system and offloading jumper was subsequently completed within a further three months, maintaining project momentum and supporting the overall accelerated development schedule. Throughout the project, 2H maintained an exemplary safety record with zero incidents, demonstrating a commitment to safe, efficient delivery under demanding timelines.

The project provided the operator with a practical, low-cost pathway to first production, transforming a marginal field opportunity into a viable development. By leveraging existing assets and adopting a phased development strategy, the platform solution significantly reduced capital expenditure, shortened the time to first oil, and minimised execution risk compared with conventional fixed platform or FPSO developments. The flexible architecture also established a scalable foundation for future field expansion, enabling the operator to align investment with production performance and long-term field objectives.

Key Personnel
Omar Khodeir

Senior Engineer

View bio
Yussof Ismail

Director, Malaysia

View bio

Project Highlights

• Wellbay platform from engineering to loadout-ready in under 6 months
• FSO mooring and offloading jumper engineered in 3 months
• Zero safety incidents throughout the project
• Low-cost early production solution for a marginal field
• Enabled a new entrant operator to plan and execute asset development with controlled costs and risks